Currently, the utility companies are performing their work along Eaglewood Drive as part of the reconstruction process. Watch for crews from Rocky Mountain Power, Google Fiber and Century Link, and please exercise caution as they work along the edge of the road.
Beginning next week, crews will begin water line work and installation of the new pressure reducing vault. Some residents will be experience water shut-offs during this process as they disconnect and reconnect the culinary water line. Affected residents will receive a water shut off notification 24-48 hours ahead of time.
Milling, or removal of old asphalt, is anticipated to begin approximately Monday, May 9th. We will know the exact date a few days prior, so watch for future project updates. The milling process will significantly impact traffic, and residents may want to plan an alternate route or adjust commute times.
Thank you for your patience as we improve the streets in your neighborhood.