Lacey Way Street Reconstruction

Recent Project Update Button

During mid-summer of 2022, Lacey Way will be reconstructed from 350 East to Nancy Way.

PURPOSE OF PROJECT

  • Replace water line in Lacey Way from 350 E. to David Way
  • Replace water line in Nancy Way from Lacey Way to Gary Way
  • Mill and overlay from 350 East to Marialana Way
  • Total street reconstruction from Marialana Way to Nancy Way

TIMELINE

  • Utility work to begin late July
  • Street reconstruction likely to begin mid-August
  • Project completion is expected by end of October

Note: Work is expected to begin at the bottom of Lacey Way.

Lacey Way Newsletter Graphic (1)

PROJECT INFORMATION MEETING

  • On July 7, 2022 the City held a virtual webinar with City Engineers, the City Manager and the contractors for the project. 

  • See page menu for the project slides as well as a recording of this webinar