September 6, 2022 Update:
The Lacey Water Line and Street Reconstruction project continues this week with crews installing water services to homes and testing the new HDPE water lines in Segment 1 of the project (between 350 E. and Marialana).
Crews will then prepare for the asphalt work by fusing pipe for the next section, performing the PVC tie-in and marking out the alignment for the new line from Marialana to Oakwood Drive, Segment 2.
Asphalt patching for the trenches of Marialana, and below, is scheduled the week of September 19, 2022. The milling and hauling away of the old asphalt of this area is scheduled for September 27-29, 2022.
Thank you.
*Dates are subject to change based on weather or other unforeseen circumstances.