475 N. Water Line & Road Reconstruction Project
4.13.23 Update:
Dear residents,
During a break in the weather, City crews were able to "zip" the old asphalt along 475 North this week to begin the process of replacing the old water pipe. Work began on the east end of 475 N. and crews are approximately 25% complete. The north side of the road is closed to parking Mon-Fri, but residents may park on the street Sat-Sun. Some driveways may be affected as the project progresses, but we will supply ramps and communicate individually with affected residents.
We are about a week behind schedule due to the weather, but we expect the water line phase of the project to last four to six more weeks, followed by Phase 2 where the old asphalt will be replaced.
Thank you for your patience.
City of North Salt Lake
Public Works